10-4 FCUU: This project involved catalyst & distillation expense
work. This consists of disassembly, cleaning, repairing and reassembling
of current equipment. A major capital project was replace the regenerator
head, cyclones and air grid along with making tie-ins to new CO
boiler. This work aks included major duct work, ato max nozzles
refractory replacement in regemerator shell, 52 reactor isolation
valve and utility tie-ins.
Ethylene Complex: Ethylene oxide, HRI & EC boilerhouse expense
work. This consisted of providing general maintenance to these facilities.
15 Plant: Overhaul 15-2A/B Gas plants. Repair the 15-2P #2 and #3
Propylene Splitters and a catalyst skim of 15-6 MTBE. The project
also included 55 variuos refinery engineered projects.
Owner:
Sun Oil Company, Inc.
KWAME Role:
Cost Controls
Architect:
N/A
KWAME Scope:
KWAME provided cost consulting services for the shutdown period.
This included all performance evaluations, system setup, cost tracking
and forecasting and tracking of all extra work.
Cost Data:
$50 million total construction cost
Timeline:
Project Duration: Shutdown Window of 6 weeks
Completed in 2000
Contact:
Mike McFarlane
Sun Company Inc.
P.O. Box 426
Marcus Hook, PA
(610) 859-1094
 |