The hospital is a pediatric facility which adjoins the existing
Barnes-Jewish Medical Complex and is part of the Washington University
Medical School. The overall project includes a vertical and horizontal
expansion and construction of approximately 77,000 square feet of
new construction and an 82,600 square foot renovation. Execution
utilizes phased construction and systems methods
Owner:
BJC Health System
KWAME Role:
Construction Management
Architect:
Cannon Architects
KWAME Scope:
As a project engineer subconsultant, KWAME provides all supervision,
facilities, and travel necessary and incidental to complete the
project engineer work as requested by the program manager, Sverdrup
Facilities, Inc.. KWAME is coordinating the architectural items
with the subcontractors and the owner as well as participating in
supplemental instruction changes and proposal request changes. In
addition, KWAME is sending out and requesting information on submittal
packages and shop drawings.
Cost Data:
$25 million total construction cost
Timeline:
Completed 1999