The project scope included design and construction at Lindbergh
Field which consisted of remodeled terminals and an eight-gate terminal
addition to lessen congestion. Enhancing roadways in and around
the airport consisted of relocation and widening to improve access.
Owner:
San Diego Unified Post District
KWAME Role:
Scheduling
Program Manager:
Parsons Infrastructure and
Technology Group, Inc.
KWAME Scope:
As a consultant to Parsons Infrastructure and Techonology Group,
Inc., KWAME provided program management services that included scheduling
and document control.
Cost Data:
$232 million total program cost
Timeline:
Completed 1998
Contact:
Loren W. Smith
Parsons Infrastructure and
Technology Group
3225 North Harbor Drive
San Diego, CA
(619) 574-4658
 |