KWAME provided Construction Management services including design
management, constructibility review, and estimating services. In
addition, KWAME led an informal Value Engineering effort which resulted
in a significant reduction in the cost of construction without changing
the design program or aesthetic impact.
The East Terminal project was divided into three bid packages.
Package A consisted of the aircraft apron and air cargo road. The
scope of Package B was the construction of the 12 aircraft gates,
while Package C included the construction of a new parking garage
and all required elevated roadways.
The project presented a number of challenges, including a small
site, limited resources, and multiple user needs. The airport wanted
to maximize available retail space. It was also important that the
airline's brand was enhanced by the terminal and that the passenger
flow was efficient.
Owner:
St. Louis Airport Authority
Architect:
Hellmuth, Obata & Kassabaum Inc.
Cost Data:
$100 million total construction cost
Timeline:
Completed - 2000
Contact:
Col. Leonard L. Griggs, Jr.,
Airport Director (Retired)
City of St. Louis Airport Authority
P.O. Box 10212
St. Louis, MO 63145
(314) 426-8000
Marjorie Melton
President, Board of Public Service
City of Saint Louis, Missouri
1200 Market Street, Room 301
St. Louis, MO 63103
(314) 622-3535
 |